JSC «GT Morstroy»
Press center
24/02/2021
We received a positive conclusion of the repeated state examination of FSUE «GLAVGOSEXPERTIZA of RUSSIA» on the project documentation and results of engineering surveys for the object «Marine transshipment complex of liquefied natural gas in the Kamchatka Territory» no. EGRZ 41-1-1-3-008055-2021 dated 24.02.2021.
We received a positive conclusion of the repeated state examination of FSUE «GLAVGOSEXPERTIZA of RUSSIA» on the project documentation and results of engineering surveys for the object «Marine transshipment complex of liquefied natural gas in the Kamchatka Territory» no. EGRZ 41-1-1-3-008055-2021 dated 24.02.2021.
The customer of the federal property facilities – FSUE «Rosmorport»
The general designer – JSC «GT Morstroy»
JSC «GT Morstroy» has consistently developed Pre-project proposals for this object, a Declaration of Intent to invest in construction, Project Documentation and Detailed Design Documentation.
The facility is designed for transshipment of liquefied natural gas (LNG) from ice-class gas carriers of the Christophe De Margerie type to floating gas storage facilities, storage of LNG and subsequent loading of LNG on gas carriers without ice reinforcement for delivery to consumers.
Facilities of the Federal property includes:
- Approach channel;
- Floating warning signs for fencing the approach channel and the water area of the Complex
- Facilities of Navigational Safety System and operational berths of Navigational Safety System
- Facilities of Engineering and technical means for transport security ensuring
- Facilities Technical Security Equipment Set KITSO of the onshore facilities of the Federal property
- Equipment of the checkpoint across the State border of the Russian Federation
11/02/2021
We received the positive conclusion from the State Environmental Expertise of the project documentation’s adjustment for «SEA TRANSSHIPMENT COMPLEX OF LIQUEFIED NATURAL GAS IN THE KAMCHATKA REGION»
The conclusion of the expert commission of the State Environmental Expertise was approved by Order No. 142 / GGE of 11.02.2021 of the Federal Supervisory Natural Resources Management Service.
Customer - LLC «NOVATEK-Kamchatka»
General Designer - JSC «GT Morstroy»
Developer of the section «Measures for the protection of the natural environment» - LLC « CAC «ECOPROJECT», Vladivostok
JSC «GT Morstroy» has successively developed Pre-project proposals for this project, a Declaration of Intent to invest in construction, Project Documentation and Detailed design Documentation.
The facility is designed for the liquefied natural gas (LNG) loading from ice-class gas carriers of the Christophe De Margerie type on floating gas storage facilities, storage of LNG and subsequent loading of LNG on gas carriers without ice strengthening for delivery to consumers.
The Expert Commission of the State Ecological Expertise established the compliance of the submitted documentation with the requirements of the legislation in the field of environmental protection.
03/02/2021
Temporary Offshore Transshipment Complex of LNG in the Murmansk Region has been commissioned
Customer – LLC «NOVATEK- Western Arctic»
General designer – JSC «GT Morstroy»
LNG Temporary Offshore Transshipment Complex in the Murmansk Region was commissioned after the testing. The test, which took place in two stages, starting from November 24, 2020, involved gas tankers «Chrostophe De Margerie», «Nikolay Yevgenov», «Yamal Spirit» and more than 10 support vessels.
On January 27-29 of this year, the planned transshipment of LNG delivered by the gas carrier with Arc7 ice class «Nikolai Zubov» from the port of Sabetta to the port of Murmansk was carried out. The cargo was reloaded at the LNG Temporary Offshore Transshipment Complex to the gas tanker with Arc4 ice-class «Yenisei River» for further delivery to consumers in China.
LLC «NOVATEK-Western Arctic» is implementing a project of the construction of the LNG Temporary offshore transshipment complex near Kildin Island in the Murmansk Region for the transshipment of liquefied natural gas from gas tankers of reinforced ice class to gas tankers without ice reinforcement with a capacity of 10.5 million tons per year.
This cargo operation is carried out in order to save transport costs for the delivery of liquefied natural gas to consumers.
We remind that the Design Institute JSC «GT Morstroy», starting in 2019, has consistently developed pre-Project proposals, Declaration of intent to invest in the construction, project and detailed design documentation for this object, and also carried out design supervision and technical support for the object construction.
The project documentation has passed all the necessary approvals and expertise.
This is the eleventh offshore transshipment complex, built according to the projects of JSC «GT Morstroy».
31/12/2020
Results of the work of the PROJECT INSTITUTE of CJSC «GT Morstroy» for 2020.
I. We have obtained a positive conclusion from the FAU «Glavgosexpertiza of Russia» for the projects:
№ п/п | Name of work | Client | Object location | №. of approval, date | Role |
1 | Estimated cost verification for the construction of «LNG Marine Transshipment Complex in the Kamchatka Region». | LLC «NOVATEK-Kamchatka» | RF, Kamchatka Region , Elizovskiy district, south-east coast of the Kamchatka Peninsula , Bechevinskaya Bay, | No. 00016-20/GGE-20796/07-01, | General designer |
2 | Project documentation and results of engineering surveys «LNG Terminal «Obskiy» | LLC «Obskiy LNG» | RF, Tyumen Region, Yamalo-Nenets Autonomous Okrug, Yamal district, Sabetta Seaport | No. 89-1-1-3-003903-2020 dated 17.02.2020 | General designer |
4 | Project documentation and results of engineering surveys «LNG Terminal «Obskiy». Waters | LLC «Obskiy LNG» | RF, Tyumen Region, Yamalo-Nenets Autonomous Okrug, Yamal district, Sabetta Seaport | No. 89-1-1-3-020937-2020 dated 28.05.2020 | General designer |
5 | Project documentation and results of engineering surveys «Ust-Luga Multipurpose Commercial Terminal» | LLC «Novotrans Active» | RF, Leningrad Region, Kingisepp district, Ust-Luga Commercial Seaport. | No. 47-1-1-3-037679-2020 | General designer |
dated 11.08.2020 |
II. Design Institute JSC «GT Morstroy» has completed the development of project, detailed design documentation and engineering surveys:
III. The construction has been begun in accordance with the projects developed by JSC «GT Morstroy»:
IV. The construction continues in accordance with the projects developed by JSC «GT Morstroy»:
V. Designer supervision is carried out:
VI. Technical support of construction is carried out:
VII. Сonstruction has been completed:
VII. Hydrotechnical facilities inspection with the development of the certificate has been carried out:
VIII. Hydrotechnical facilities inspections with the development of updated part of the certificate have been carried out:
IX. Changes in the certificates of hydrotechnical facilities:
X. Subsea technical works:
XI. Survey of aboveground buildings and structures:
Activities
Front end engineering design (FEED)
Business planning
Engineering surveys
Desing
Desinger supervision
Certification of hydrotechnical facilities